Opening a restaurant in Houston, the permit path

A step-by-step checklist for opening a brick-and-mortar restaurant in Houston: registration, plan review, health permit, inspections, fire, signs and alcohol.

Opening a restaurant in Houston means getting approval from more than one office, in a particular order, before the first customer is served. The steps are not secret, but they live on several different websites and phone lines, and it is easy to do them out of order and lose weeks. This checklist puts them in sequence for a new, brick-and-mortar restaurant inside the City of Houston. It follows the city's own descriptions of the process, and it leaves fees and fine print to the offices that set them.

A note on scope: the steps here apply to permanent restaurants in buildings. Food trucks and other mobile units follow a different process, covered in food trucks and city permits, and temporary events and farmers markets follow others. A restaurant outside the City of Houston's limits, in unincorporated Harris County or another city, answers to a different set of offices.

Before the steps: no zoning, but still rules

Houston has no zoning. The city does not divide its land into districts that decide where a restaurant may open, a feature explained in Why Houston has no zoning and how development is governed instead. That is a real advantage for an operator looking for space, because a restaurant can be considered for many kinds of buildings.

But "no zoning" does not mean "no rules." The building must meet the city's building code for the use. Private deed restrictions on a property can limit what a building may be used for, and an operator should read the restrictions on any site before signing a lease or buying. The health, fire and other permits below apply wherever the restaurant is. A site that looks ideal can still fail on plumbing, grease handling, parking or occupancy, so check the building early.

The checklist

1. Register the business

Before dealing with the city, set up the business itself. In Texas, a business that operates under a name other than the owner's legal name files an assumed name certificate, and in Harris County the County Clerk handles those filings. Many owners also form a company through the state. The city's business portal and the guide in Starting a business in Houston explain the early steps. Separately, businesses that sell taxable items need to register with the state for sales tax; the state Comptroller handles that.

2. Find and vet a site

Choose the space, then check it. Ask the landlord or seller about the building's permitted use, its certificate of occupancy and its plumbing, and read any deed restrictions. A building that was never a food establishment will need more work than one that was.

3. Decide whether plans are required

The Health Department says plans are needed for new construction, for remodeling a space that was never a food establishment, for room additions or changes to walls, floors or equipment, and when the scope of food service changes. Taking over a permitted business without changes may not require plans. The inspector makes the final decision, so ask before assuming.

4. Prepare the plans

If plans are required, they must be drawn to scale and include a floor plan with the equipment layout, equipment specifications, elevations of food equipment and plumbing fixtures and a room finish schedule. A remodel also needs drawings of the existing space, the demolition and the proposed layout. The Health Department offers a Food Inspection Plan Submission Checklist for this. Most operators hire a designer or architect familiar with the process.

5. Submit plans to the Houston Permitting Center

Submit two sets of plans and specifications to the Commercial Plan Review Section of the Houston Permitting Center, at 1002 Washington Avenue, Houston 77002, and include the Food Dealers Permit Application. The Health Department's plan review section is on the third floor of the building. The center is described in Houston Permitting Center and the building permit process in Getting a building permit in Houston. The center's commercial plan review line is 832-394-8810 and the health plan review line is 832-394-8848, and the center's hours are posted on its site.

6. Build to the approved plans

When the plans are approved, build the kitchen as drawn. If you need to change something during construction, get approval for the modified plans before you proceed. A change made without approval can fail the final inspection.

7. Name a certified food manager

The Health Department asks for the name, phone number and email of the certified food manager who will be on site for the pre-operational inspection. Certification comes from an approved course; the department's food manager and food handler certification page lists the requirements, and weekly manager certification classes are offered, with fees. Staff who handle food but are not managers need food handler training.

8. Schedule the pre-operational inspection

Call the Consumer Health Services Permit Office at 832-393-5100 to schedule the inspection. The department asks that you book at least 14 business days in advance. Have the stamped plans on site if plans were required. An inspector will contact you before the appointment, and a fee is charged for each pre-opening inspection. If the kitchen does not pass, you will need to correct the problems and schedule another.

9. Pass, pay and get the permit

If the kitchen complies, the department issues an invoice for all required permits. You take the invoice to the environmental permit office on the first floor at 8000 North Stadium Drive and pay. The accepted payments are company checks, Visa, Discover, MasterCard and debit cards, and American Express is not accepted. Payments made at the Permitting Center or online are processed and the permit printed only at the Stadium Drive office. You may pick up the permit in person or receive it by mail.

10. Handle the other approvals

The health permit is not the only requirement. Several others may apply:

  • Certificate of Occupancy. Houston Public Works issues the certificate of occupancy, which confirms that the building can be used for the intended purpose.
  • Fire Marshal permits. The Houston Fire Marshal's office issues permits related to public assembly, maximum occupancy and flammable materials, where they apply to the business.
  • Signs. Building Code Enforcement at the Permitting Center handles sign permits, so any exterior sign needs approval.
  • Commercial permits. The city's Administration and Regulatory Affairs department issues certain yearly permits, for activities such as amusement machines or loudspeakers.
  • Alcohol. A restaurant that serves alcohol needs a license from the Texas Alcoholic Beverage Commission.
  • Grease. The Health Department lists grease trap inspections among its services, and a kitchen has to manage grease properly.

11. Operate within the permit

Once open, you may not operate without a valid permit. The permit is non-transferable, must be posted where the public can see it and must be renewed every year. Inspectors continue to visit. The system is explained in How a Houston kitchen gets permitted and inspected.

A sample sequence in time

The order matters more than the dates, because the city does not publish a single timeline for the whole process. An illustrative sequence for a hypothetical operator might look like this:

Stage What happens
Months before opening Choose the site, check deed restrictions, hire a designer, register the business
Plans Submit plans and the permit application; wait for review and corrections
Construction Build to the approved plans; submit any changes for approval
About three weeks before the hoped-for opening Request the pre-operational inspection, which needs at least 14 business days' notice
Inspection Pass, or correct and reschedule
Permit Pay and receive the health permit
Opening Open with all other approvals in place

The best advice is to start the inspection request as soon as the construction schedule is firm, since the 14-business-day notice is the one fixed delay.

Counting the 14 business days

The notice period is the one number in the process that a planner can calculate, and it is easy to miscount. Business days exclude weekends and, in general, official holidays. Say, hypothetically, that an operator calls on Monday, November 2 to request the pre-operational inspection. Counting business days from the next day, Tuesday, November 3 is day 1, Friday, November 6 is day 4, Friday, November 13 is day 9 and Friday, November 20 is day 14. So the earliest the department asks for is about November 20, which is nearly three calendar weeks after the call, and a holiday in the middle would push it later. An operator who tells a landlord, a staff and a marketing team that the restaurant opens on November 16 has made a mistake that the calendar will not forgive.

The practical advice is to make the call as soon as the construction finish date is reliable, and to treat the earliest possible inspection as a floor, not a promise.

What to budget for

Fees are set in the city's fee schedule and change from time to time, so build a budget from the current schedule. The categories of cost to include are:

  • Design and plans. The fees of the architect or designer who prepares the drawings.
  • Plan review and permit fees. Charges from the Permitting Center and the Health Department.
  • Inspection fees. A fee for each pre-opening inspection, so a failed inspection that needs a second visit costs more.
  • Construction and equipment. The build-out, kitchen equipment and any grease management.
  • Certification and training. The food manager course and food handler training for staff.
  • State and county filings. The assumed name filing, any company formation and sales tax registration.
  • Other permits. Fire, signs and alcohol licensing, each with its own fees.
  • Time. The weeks of rent paid while waiting for approvals, which is often the largest hidden cost.

The last item is worth dwelling on. A lease that starts before the permit does means paying rent on a space that cannot earn. Operators often negotiate a rent-free period or a start date tied to permits for this reason.

Questions new operators ask

Do I need a food manager certificate before I open? The Health Department asks for the name of a certified food manager who will be on site for the pre-operational inspection, so yes, someone has to be certified in time.

Can I take over an existing restaurant without new plans? If you are taking over a permitted business without changes to the layout or scope, plans may not be required, but the inspector decides, and you still need your own permit.

What if I want to change the menu later? A significant change in the scope of food service can trigger a plan requirement. Ask the department before making a change that adds new kinds of food preparation.

Where do I pay? Health permit payments are made at the environmental permit office at 8000 North Stadium Drive, not at the Permitting Center.

Does the city have a handbook? The city's business portal and the Health Department's pages describe the steps. The department's plan review staff can answer questions before you submit.

What about a restaurant inside a food hall or market? Food halls, markets and temporary events may follow different processes. See the farmers market and food hall discussion in houston farmers markets and food halls and ask the department which process applies.

Common ways the process goes wrong

  • Starting construction before plans are approved. Work done to unapproved plans may have to be redone.
  • Forgetting a separate approval. The fire, sign and alcohol approvals run on their own timelines.
  • Not booking the inspection early. A delay in scheduling delays the opening.
  • Assuming a permit transfers. A new owner of an existing restaurant needs their own permit.
  • Skipping the building check. Plumbing, grease and occupancy problems found late are expensive.

Where to ask

The city's business portal at houstontx.gov/business leads to the offices above. The Houston Permitting Center and the Health Department can answer questions about a specific project, and the contact details and fees are on their sites, since both change. This is general information, not legal or professional advice. For help with the county side, such as an assumed name filing, see Harris County Government.